Neubau Forschungsgebäude Cispa

Research Building CISPA

This is a custom heading element.

In a tight timeframe of only 21 months, a four-story institute building was designed and built for the University of Saarland, creating a gatehouse situation for the university's eastern entrance.

The CISPA Centre for IT Security, Privacy and Accountability, was recently given an award as one of three lighthouses for IT security in Germany, and represents a focal point for informatics in Saarbrücken.

135 work places, meeting and conference areas and an auditorium have been created around a generous illuminated foyer four-storeys high. The atrium cascades over the four floors and thus forms work and communication zones on each floor. This cascade is legible on the west façade in a stair-like arrangement of glazed surfaces. On the ground floor, full-height glazing encloses presentation rooms, larger lecture rooms and the auditorium. On the first to third floors offices and meeting rooms in a range of sizes are located.

Hybrid Design Build

One characteristic of the new building is the austere façade with stepped ribbon-like bands of windows and parapets. These clustered modulations reveal the IT functions within the building.

The special caracteristic of this project is the way of its planning and implementation as hybrid design build. In the unusually brief period of only 21 months from the award of contract award and the start of planning through to handover to the client, the building was designed, planned, approved and implemented. For this, the client and the user, the general contractor and the architect have come together to form a tight construction team and the building developed together in very close period.

 

Location
Campus E9.1, 66123 Saarbrücken
Client
University of Saarland
Architects
Veauthier Architekten
Services
Architectural design phases 1-5
Completion
2015
Size
5.230 m2 BGF
Image rights
Veauthier Architekten


Campus Center

This is a custom heading element.

The design for the new Campus Centre at the University of Saarland was developed on the basis of the urban planning framework that was planned in cooperation between Veauthier Architects and the Machleidt Office of Urbanism, Berlin. The building serves functionally and spatially as a new focal point for the campus. It combines several central advisory and service facilities as well as student spaces; on the ground floor there is a range of shops and commercial units.

The central campus square, a former parade ground, is framed by the new, 90 metre long, two-storey building, making its original, strict orthogonality visible once again.

The cantilevered canopy of the Campus Centre expresses a welcoming and protective gesture. The illuminated roof is clad with translucent polycarbonate panels both above and below. During the day natural light enters through the roof, while at night the building is transformed into an architecture of light.

The staggered vertical façade elements give the new building a musical style. The structure is based on a regular, irregular rhythm that can be read as a kind of musical notation. It gives the façade a lively and balanced appearance.

Location
Campus A4.4, 66123 Saarbrücken
Client
University of Saarland
Architects
Veauthier Architekten
Services
Architectural design phases 1-8
Completion
2010
Size
2.220 m2 BGF
Bildrechte
Christoph Rokitta


Institutsgebaeude fuer Sprachforschung Veauthier

Institute of Computational Linguistics

This is a custom heading element.

The new building for the Institute for Linguistic Research and Language Technology was the first component of the joint urban planning framework by Veauthier Architekten and the Machleidt urban planning office for Saarland University.

With its classic form, the solitary building establishes a relationship to the neighbouring buildings from the 1960s and yet remains recognizable as a modern university building of the 21st century. This is ensured by elements such as the black-colored prefabricated exposed aggregate concrete elements and vertical offsets in the façade.

The three-storey entrance hall, glazed on two sides, forms the communicative and spatial center of the building, i.e. the heart of the institute, from which the interior areas, arranged on a total of five split levels, are accessed. The spacious platform areas, equipped with lounge furniture, invite people to linger, read and relax.

Location
Campus C7.4, 66123 Saarbrücken
Client
Ministerium für Bildung, Kultur und Wissenschaft des Saarlandes
Architects
Veauthier Architekten
Services
Architectural design phases 1-5
Completion
2003-2005
Size
1.790 m2 BGF
Image rights
Werner Huthmacher


Neubau UmweltHaus der UmweltBank AG Nürnberg

Project management of an highrise timber office building UmweltBank

This is a custom heading element.

UmweltBank is planning a sustainable urban quarter at Nuremberg's Nordwestring 101. The new headquarters of the company, the UmweltHaus, will be realized as the first building block, as one of the first office buildings in Germany according to the energy efficiency standard KfW Effizienzhaus 40 NH with a platinum certification of the German Sustainable Building Council (DGNB) an.

The UmweltHaus is designed as a conceptually sustainable building in construction and operation. With its combination of consistent timber construction and large-scale facade PV, the UmweltHaus clearly stands out from other building projects. Construction completion is planned for 2025.

As Managing Director of the pro.b Group, Andreas Veauthier is responsible for project management from phase zero in 2019 to the shell construction in 2023.


Further informations:
https://www.umweltbank.de/info/standort

Location
Nordwestring, 90419 Nürnberg
Client
UmweltBank AG
Architects
Spengler Wiescholek Architektur Stadtplanung PartGmbB, Hamburg
Energetic
Standard
KfW Efficiency House 40 NH, timber hybrid construction, façade-integrated photovoltaics, low emissions, DGNB Platinum with Diamond
Services
Project management from project development to shell construction as as Managing Director of the pro.b Group
Size
24.000 m2
Processing time
2019-2023
Image rights
Spengler Wiescholek Architektur Stadtplanung PartGmbB


Project management of a wooden student residence

This is a custom heading element.

The project has been developed in wood hybrid and wood modular construction and will expand the housing options for students in the Environmental Quarter in the future. The smallest unit in the design, the single apartment, is designed as a module and cleverly coupled with the multi-person apartments so that the six upper floors can be built in classic modular timber construction.

The solid base distributes the resulting loads with a strong ceiling that minimizes any interference from columns or load-bearing elements on the first floor. The design idea is derived from the timber hybrid construction method. Consequently, the upper floors have a wood facade with large window openings cut into it. The entire southwest façade is covered with monocrystalline PV elements from the second floor upwards. Their dimensions are adapted to the structure of the building.

The development plan process for the UmweltQuartier is currently underway in coordination with the City of Nuremberg. UmweltBank's goal is to create a sustainable and liveable urban neighborhood with high ecological and social standards. In addition to living space for students, the plans include social and affordable housing, a daycare center, commercial space, and spacious, publicly accessible play and green spaces.

As Managing Director of pro.b Group, Andreas Veauthier is responsible for project management from phase zero in 2019 until the end of the architectural competition in 2023.

Location
Nordwestring, 90419 Nürnberg
client
UmweltBank AG, Nürnberg
Architects
Peter W. Schmidt Architekten, Berlin
Services
Project management from project development to completion of the architectural competition as Managing Director of the pro.b Group
Size
6.600 m2 BGF
Processing time
2022-2023
Image rights
Peter W. Schmidt Architekten, Berlin

Project management of residential construction in timber hybrid construction

This is a custom heading element.

The development plan process for the UmweltQuartier on Nordwestring in Nuremberg is currently underway in coordination with the City of Nuremberg. UmweltBank's aim is to build a sustainable and liveable urban quarter to high ecological and social standards. In addition to residential buildings in timber hybrid construction, a student residence, a daycare center, commercial space and spacious, publicly accessible play and green areas are also planned.

Quartier 4 envisages three point blocks in timber hybrid construction. The basic structure of the building consists of load-bearing wall bulkheads made of cross-laminated timber, which are braced by a reinforced concrete core. On the short sides, the bulkheads also form the outer walls; on the long sides, the façade is non-load-bearing, which allows for easy projections and recesses. The non-load-bearing timber façade has a modular structure. The individual modules differ depending on their function: balcony railing, parapet, solar panel, window strip - these mosaic tiles create a varied yet orderly façade appearance.

Location
Nordwestring, 90419 Nürnberg
client
UmweltBank AG, Nürnberg
Architects
Pakula Fischer Architekten, Stuttgart
Services
Project management from project development to shell construction as member of the pro.b group
Size
7.500 m2 BGF
Processing time
2021-2023
Image rights
Pakula Fischer Architekten, Stuttgart

Punkthäuser

Project management of timber houses Auwiesen Wangen

This is a custom heading element.

The town of Wangen im Allgäu will host the Baden-Württemberg State Garden Show in 2024. As part of this garden show, a new attractive residential area has been created on the Auwiesen site. On the approx. 3,500 m² site, 98 new rental apartments are currently being built in so-called "point houses". Against the backdrop of the State Garden Show, the new development will make an important contribution to the themes: Innovation timber construction, renewable raw materials, climate protection, sustainability and future-oriented forms of construction. For example, all three buildings were constructed using hybrid timber construction.

The aim of the planning was to plan and implement the three point buildings in a high-quality, economical and sustainable manner. The planning provides a high-quality response to the given urban planning, functional and economic requirements. For this reason, the three point blocks were built as timber hybrid buildings in KfW 40 plus construction. Photovoltaic systems were installed on the roofs, which are billed via a tenant electricity model.

Andreas Veauthier hatte als GF der pro.b Gruppe von der Phase Null in 2018 bis zum Rohbau in 2020 die Projektsteuerung inne. Die Baufertigstellung ist für Sommer 2024 vorgesehen.

Video der Holzbau-Offensive Baden-Württemberg

Location
Auwiesen, 88239 Wangen
Client
Volksbau Wangen GmbH & Co KG
Services
Project management from project development to start of construction
Architects
Rogg Architekten, Konstanz
Processing time
2018-2020
Image rights
Holzbau-Offensive Baden-Württemberg

 


Wohnungsbau Matthiasstrase

Matthiasstrasse residential building

This is a custom heading element.

The seven-storey apartment building marks a corner plot in Berlin's densely built-up inner-city district of Friedrichshain. The building is adjacent to the listed Georgen-Parochial cemetery and benefits from its park-like atmosphere. While the commercial first floor areas are enclosed by the high cemetery wall, the upper floors open up to the street with generously glazed loggias to the south and west. The floor plans thus provide residents with both a connection to the hustle and bustle on the street and a view of the greenery.

The design features a mix of 1.5-room apartments and larger 4-room apartments. All residential units have balconies or terraces. The floor-to-ceiling glazing creates a generous sense of space, especially in combination with the attractive outdoor space.

The storey ceilings are visible in the façade and, together with the continuous railings, give the building a strict horizontal structure.

Location
Matthiasstraße 11, 10249 Berlin-Friedrichshain
Client
UTB Bauträger und Projektmanagement GmbH
Architects
Veauthier Meyer Architekten
Completion
2011-2012
Size
3.200 m2 BGF

Flottwellstrasse residential building

This is a custom heading element.

The seven-storey apartment building was built as part of a larger project development as one of a total of ten houses for building cooperatives on a former industrial wasteland in the center of Berlin. Veauthier Architekten developed the building in close consultation with the client group and combined very different forms of living under one roof.

The first floor and second floor are shared by three apartments, which are organized like two-storey townhouses. They each have their own entrances from the street and a garden in the courtyard. The staircases to the townhouses serve as a buffer to the public street and have small front gardens. While the townhouses tend to be closed towards the street, they are generously glazed on the ground floor towards their gardens and have large balconies on the upper floor. Translated with www.DeepL.com/Translator (free version)

The other upper floors each house a small and a large family apartment, while spacious maisonettes with roof terraces extend over floors six and seven. The building does not keep this typological diversity to itself - its internal structure can also be seen on the façade. Projections and recesses as well as continuous railings on the street side emphasize the horizontal division of the building into different residential typologies.

Die Mischung von Wohnungsgrößen und Raumprogrammen öffnet das Haus für eine Bewohnerschaft mit unterschiedlichen Lebensentwürfen, Familienstrukturen und Haushaltsgrößen.

Location
Flottwellstraße 9-12, 10785 Berlin-Tiergarten
Client
Baugemeinschaft Metropolis 1 GbR
Architects
Veauthier Meyer Architekten
Energiestandard
KfW NH 55
Services
Architectural design phases 1-5
Completion
2013
Size
1.250 m2 BGF
Image rights
Veauthier Architekten

 


Haasestrasse residential building

This is a custom heading element.

The Baugemeinschaft Haasestraße (property development cooperative) has erected six modern new buildings with a total of around 80 apartments and commercial units in the Revaler Strasse quarter. The block, which previously only contained small businesses, was closed off for the first time by a perimeter block development.

Veauthier Architekten planned the six-storey building 2 with 12 apartments and underground parking. Each floor has two units with living spaces of between 110 and 125 m2. The first floor was built as a half-storey offset mezzanine with ground-level access to the garden/courtyard. On the one hand, this provides privacy from the street, while on the other, it allows an economical solution for the underground garage. On the upper floors, open-plan living is favored: each apartment has balconies facing the street and the courtyard. The two top-floor apartments have terraces that extend across the entire width of the building.

The alternation of light plaster surfaces and dark windows gives rhythm to the façade.

Location
Haasestraße 2, 10245 Berlin-Friedrichshain
Client
Baugemeinschaft Haasestraße GbR
Architects
Veauthier Meyer Architekten
Energiestandard
KfW NH 55
Services
Architectural design phases 1-5
Completion
2016
Size
1.250 m2 BGF
Image rights
Veauthier Architekten

 


Bernstein Centre for Computational Neuroscience

This is a custom heading element.

Teilbereiche des denkmalgeschützten Gebäudes der ehemaligen Tieranatomie aus dem Jahr 1906 wurden umfangreich instandgesetzt und energetisch optimiert. Für den neuen Nutzer, das Bernstein Zentrum für Computational Neuroscience Berlin, wurden Büro-, Labor- und Seminarräume sowie eine kleine Spezialbibliothek geschaffen.

Sämtliche Maßnahmen des Wärmeschutzes, wie z. B. Innenwanddämmung sowie Isolier- anstelle von Einfachverglasungen fügen sich in den Gesamtkontext der vorhandenen Gebäudestruktur ein. Maßgeschneiderte Lösungen bringen die Anforderungen aus Brandschutz und Barrierefreiheit mit den Belangen des Denkmalschutzes in Einklang. Heizungs-, Lüftungs- und Sanitäranlagen wurden vollständig erneuert.

Location
Charité Campus, Philippstraße, 10115 Berlin-Mitte
Client
Humboldt-Universität zu Berlin
Architects
Veauthier Meyer Architekten
Services
Objektplanung und Freianlagen LP 1–8, Brandschutzkonzept, Berechnungen nach EnEV 2009
Size
1.050 m2 BGF
Image rights
Christoph Rokitta

 


Gästehaus Leibniz Zentrum für Informatik

Guesthouse at the Leibniz Center for Informatics

This is a custom heading element.

In 2011, a new guesthouse was added to the baroque, landmarked Dagstuhl Castle complex, now home to the Leibniz Center for Informatics. The challenge was to develop an architecturally appealing, harmonious relationship between the new building and the historic building, which had been expanded several times in the post-war period.

The guest house, clad in a wooden slatted facade, appears to rest like an elegant cube on the surrounding wall at the end of the castle garden, and at the same time extends beyond it with a wide cantilevered terrace. With this open yet sheltered area, the house creates a new link between the castle grounds and the surrounding meadows.

The project received the Saarland Building Owner Award in 2014. From the jury's comments: "The high art of solving a challenging task in a seemingly simple way is evident not only in an almost self-explanatory building design, but also in every recognizable detail. The consistency of the implementation from design to construction planning to execution is impressive".

Location
Schloss Dagstuhl, 66687 Wadern
Client
Leibniz-Zentrum für Informatik GmbH
Architects
Veauthier Meyer Architekten
Services
Architectural design phases 1-8
Completion
2011
Image rights
Veauthier Meyer Architekten
Awards
Award of the Saarland Chamber of Architects 2014

 


Saarland Ministry of Cultural Affairs

This is a custom heading element.

Der ehemalige Sitz des Kultusministeriums des Saarlandes, der sogenannte Pingusson Bau, wurde von dem französischen Architekten Georges Henri Pingusson als Gebäude der Französischen Botschaft entworfen und 1954 fertiggestellt. Der denkmalgeschützte Gebäudekomplex besteht aus einer neungeschossigen Hochhausscheibe (der ehemaligen Kanzlei) und einem aufwändig ausgestatteten zweigeschossigen Flachbau (der ehemaligen Residenz des Botschafters). Das Hochhaus wurde als ungedämmter Stahlbetonbau errichtet, der Flachbau als Mischkonstruktion.

Wegen massiver Schäden an den Betonfassaden und vielfältiger energetischer und technischer Mängel sollte der gesamte Gebäudekomplex grundlegend saniert werden.

Das Büro Veauthier Meyer erarbeitete eine umfassende Bestandsaufnahme mit bauhistorischer Dokumentation, digitalem Planwerk, Fotodokumentation mit Raumbuch und Dokumentation der historischen Gebäudetechnik. Auf Grundlage der Bestandsaufnahme und verschiedener Fachgutachten (Beton, Bauphysik, Bauklimatik, TGA) wurden denkmalgerechte Varianten der Fassadensanierung erarbeitet und gegeneinander abgewogen.

Location
Hohenzollernstraße 60, 66117 Saarbrücken
Client
Ministerium für Bildung, Familie, Frauen und Kultur des Saarlandes
Architects
Veauthier Meyer Architekten
Services
Bestandsaufnahmen, Fassadensanierung LP 1-5
Completion
2007-2008
Size
12.200 m2 BGF

 


Zielplanung Christian-Albrechts-Universität Kiel

This is a custom heading element.

Im Jahr 2008 wurde das Kernensemble des Campus der Christian-Albrechts-Universität in Kiel unter Denkmalschutz gestellt. Es besteht aus Gebäuden aus den 1930er bis 1970er Jahren mit hoher geschichtlicher, städtebaulicher, architektonischer und künstlerischer Bedeutung. Zu den Elementen der denkmalgeschützten Gesamtanlage zählen neben den Gebäuden ebenso die Freiflächen und die künstlerische Ausstattung.

Im Rahmen der umfangreichen Studie wurden auf Grundlage von Bestandsaufnahmen und –analysen denkmalpflegerische Zielplanungen für das gesamte Ensemble erstellt.

Die Umsetzungen der Zielplanungen werden ab 2015 initiiert.

Location
Christian-Albrechts-Universität, 24118 Kiel
Client
GMSH Gebäudemanagement Schleswig-Holstein AöR
Architects
Veauthier Meyer Architekten
Services
Bestandsaufnahmen, Bestandsanalysen und Gebäudebewertungen, Planungsmaßnahmen
Completion
2010
Size
88.000 m2 BGF

 


WEW

This is a custom heading element.

Die Stadt Erfurt beschloss Mitte der 1990iger Jahre, das Wohngebiet ‚An der Weinsteige‘ in ruhiger Lage im Ortsteil Bindersleben zu errichten.

Das Entwurfskonzept trägt der steigenden Nachfrage nach flexibel nutzbarem, individuellem und zugleich bezahlbarem Wohnraum Rechnung. Die Reihen-, Ketten- und Doppelhäuser werden ökonomisch optimiert hergestellt, sind aber durch edle Details sowie durch praktische und veränderbare Nutzungsfunktionen hochwertig und zugleich entsprechend der sich wandelnden Vorstellungen ihrer Nutzer veränderbar.

Aus dem Wechselspiel von Reihen-, Ketten- und Doppelhäusern ergeben sich durchgängige Zeilen, die in Höhe, Tiefe und Fassadenrelief räumlich differenziert sind. Die modularen Abmessungen gewährleisten verschiedene Kombinationsmöglichkeiten der Typen innerhalb der Baufenster und Baufelder. Dadurch kann flexibel auf Nutzernachfragen und Kostenkalkulationen des Bauherren reagiert werden.

Die Einheitlichkeit der verwendeten Fassadenelemente schafft einen gemeinschaftlichen Ausdruck und bildet damit den Hintergrund für individuelle Wohnkonzepte der Bewohner.

Location
An der Weinsteige, 99092 Erfurt-Bindersleben
Client
R&S Bau Beteiligungs GmbH
Services
Objektplanung LP 1-4
Completion
2003

 


Scheer Tower

This is a custom heading element.

Der Neubau des Scheer Towers ist das erste von drei vorgesehenen Hochhäusern im Norden des Universitätscampus. Das elfgeschossige Gebäude mit einem hangseitig vorgeschobenen Untergeschoss bietet Büroarbeitsplätze für 240 Mitarbeiter.

Im Erdgeschoss und im Untergeschoss befinden sich gemeinsam genutzte Einrichtungen wie Foyer, Cafeteria und Veranstaltungsräume. In den neun darüber liegenden Obergeschossen gruppieren sich Büros, Besprechungs-, Kommunikations- und Nebenräume um einen zentralen Erschließungs- und Versorgungskern. Einzelne Etagen können bei Bedarf zu Nutzungseinheiten zusammengefasst werden. Im obersten Geschoss sind Konferenzräume und eine offene Dachterrasse mit einem weiten Blick in die Landschaft angeordnet.

Die Fassade aus rot beschichteten Aluminium-Blechen lässt das Gebäude als Landmarke über dem Universitätscampus erscheinen.

Location
Campus D5.1, 66123 Saarbrücken
Client
Prof. Dr. Dr. h.c. mult. August Wilhelm Scheer
Architects
Veauthier Meyer Architekten in ARGE mit Planungsgruppe Focht und Partner
Services
Objektplanung/Freianlagen; Veauthier Meyer Architekten LP1-5, Planungsgruppe Focht und Partner LP6-9
Completion
2012
Size
6.300 m2 BGF
Image rights
Veauthier Meyer Architekten

 


Masterplanning Saarland University

This is a custom heading element.

Das Konzept strukturiert die künftige Entwicklung und macht Vorschläge zur Aufwertung des überkommenen Erscheinungsbildes der Universität.

Ziel war es, einen reizvollen Kontrast zu schaffen zwischen einem verdichteten Kernbereich mit städtischer Ausprägung und den in eine offene, bewegte Parklandschaft eingebetteten Campus mit den Institusgebäuden aus vorwiegend jüngerer Zeit. Die Grenzen zum umgebenden Stadtwald wurden neu und eindeutig definiert. Die ursprüngliche, wohltuende Anmutung der ‚Universität auf der Lichtung‘ wurde wieder hergestellt.

Location
Campus, 10119 Saarbrücken
Client
Ministerium für Finanzen des Saarlandes
Architects
Veauthier Architekten
Services
Bebauungsstudien, Städtebauliche Entwürfe, Visualisierungen, Stellplatz- und Verkehrskonzept, Freiraumplanung
Completion
2002
Size
45 ha
Kooperation
Machleidt Büro für Städtebau, Thomanek Duquesnoy Boemanns, GRI Berlin

 


Public Swimming Pool Niestetal

This is a custom heading element.

The nearly square building is a prototype for our concept of the new urban bathroom: compact and energy-efficient.

Due to the risk of flooding on the site, the building does not have a basement and the bathing area is located on the upper floor. The building is accessed via a ground floor lobby with direct access to the elevator, accessible restrooms, and the rear areas of the first floor with staff locker rooms, recreation and storage areas, and access to the technical facilities. The upper floor is accessible via the adjacent staircase as the pool level with foyer and cashier area. The L-shaped pool area is accessible via the compact layout of the locker rooms and sanitary facilities. This area is divided into a multi-purpose pool, a toddler pool and a separable area for a lap pool. The design includes a highly insulated concrete structure on the first floor with a ventilated aluminum profile facade. The hall areas on the upper floors are designed as exposed concrete wall panels with a mineral insulated VHF facade. The opening areas have a mullion-transom facade with triple insulating glazing. Between the walls, in the area of the indoor pools, there are steel beams on which are placed wooden elements with an integrated acoustic effect.

Location
34266 Niestetal
Client
Gemeindewerke Niestetal
Architects
av-a Architekten GmbH
Services
Objektplanung LP 1–8
Completion
2024
Size
3.500 m2 BGF
Image rights
Teodor Hribovsek


Gotha Municipal Pool

This is a custom heading element.

Das denkmalgeschützte Stadtbad im thüringischen Gotha eröffnete 1909 als zeittypisches Volksbad. Der Jugendstilbau (Entwurf: Wilhelm Goette) diente bis zur Wende als städtische Schwimmhalle und wurde nach dem Verkauf an einen Privatinvestor geschlossen. Im Anschluss an den Rückkauf der Liegenschaft durch die Stadt im Jahr 2007 fand ein europaweiter Architekturwettbewerb statt, bei dem es darum ging, das historische Gebäude in einen neu entstehenden, barrierefreien Sport-, Gesundheits- und Freizeitkomplex zu integrieren.

Das städtebauliche Konzept der Erweiterung ergänzt das historische Bad an seinen Flanken um zwei moderne Neubauten. Auf der östlichen Seite nehmen sie die große neue Saunalandschaft auf, auf der westlichen Seite fanden das wettkampftaugliche 25-Meter-Becken und das Lehrschwimmbecken Platz. Die markante Kubenform der niedrigen Neubauten ergibt sich aus der Umgebungssituation: Dank ihrer geringeren Gebäudehöhe wird der benachbarte Altbaubestand in dem dicht bebauten Areal nicht verschattet. Bei der Belichtung der Baukörper selbst wurde auf die ursprüngliche Lösung – in moderner Form – zurückgegriffen: das neue Bad wird von Tageslicht erhellt, das großzügig von den Längsseiten und der Stirnfläche einfällt. Den Übergang vom Alt- zum Neubau markiert eine neue Treppenanlage, die zugleich als Tribüne und Aufenthaltsbereich dient.

Das so gefasste, denkmalgerecht sanierte historische Gebäude wird nach den 2014 abgeschlossenen Baumaßnahmen als kommunikatives und atmosphärisches Zentrum des Ensembles genutzt. Das historische Schwimmbecken steht nach seiner baulichen und gestalterischen Revitalisierung für Gesundheitskurse und -anwendungen zur Verfügung; die ehemaligen Saunaabteilungen dienen als Aufenthalts- und Ruhezonen. Im Zuge der Sanierung der denkmalgeschützten Substanz wurden auch erhaltene Details wie historische Fliesen und Bodenbeläge nach historischem Vorbild restauriert.

Location
Bohnstedtstraße 6, 99867 Gotha
Client
Stadtverwaltung Gotha
Architects
Veauthier Meyer Architekten
Services
Objektplanung und Planung Freianlagen LP 1–8, Denkmalpflegerische Bestandsaufnahme
Completion
2014
Size
8.400 m2 BGF
Image rights
Klemens Ortmeyer
Anerkennungen
Anerkennung im Baukultur Preis Thüringen 2014
Anerkennung im BDA Preis Thüringen 2015
Anerkennung im Thüringer Staatspreis für Ingenieurleistungen und Holzbaupreis 2015

 


Indoor Swimming Pool Finckensteinallee

This is a custom heading element.

Bei der Sanierung der Schwimmhalle im Süden Berlins kam es nicht nur auf die intelligente Integration von technischen und denkmalpflegerischen Maßnahmen an, sondern vor allem auf einen gestalterisch sensiblen Umgang mit der historischen Substanz.

Die 1938 eröffnete Anlage (Entwurf: Karl Reichle und Karl Badberger) entstand auf dem Gelände einer ehemaligen Kadettenanstalt und diente ursprünglich der Ertüchtigung der SS-Leibstandarte. Das wettkampftaugliche Bad mit einem 25 mal 50 Meter großen Becken gehörte zum Zeitpunkt seiner Fertigstellung zu den größten und modernsten Schwimmsporthallen Europas. In den Nachkriegsjahrzehnten wurde die Anlage von den in Berlin stationierten US-Alliierten genutzt, bis sie 1994 in den Bestand der Berliner Bäderbetriebe überging. 2006 musste die Halle dann aufgrund von Verschleiß und Baumängeln geschlossen werden.

Die Sanierung erfolgte nach einem architektonischen Konzept, das zwischen Erhaltung, Wiedergewinnung und Weiterentwicklung verschiedener Bauteile und Raumgruppen differenzierte. Während es bei den erhaltenden Maßnahmen um die gleichzeitig behutsam optimierte Außenhülle ging, galt es, der Schwimmhalle vor allem durch die Ausbildung der neuen Decke jenen Raumeindruck wiederzugeben, der sie noch bis in die 1970er Jahre prägte. Die Weiterentwicklung erfolgte vornehmlich in den Bereichen von Duschen und Garderoben, denen mit einem neuen Farbkonzept ein starker Ausdruck verliehen wurde.

Die Sanierung und Modernisierung des Bauwerks mit seiner Backsteinfassade im Monumentalstil umfasste neben der denkmalgerechten Renovierung der Gebäudehülle auch eine grundlegende Erneuerung der technischen und funktionalen Strukturen sowie die Anpassung der gesamten Anlage an zeitgemäße energetische Standards. Außerdem wurden erhaltene historische Details wie Reliefs, Naturstein- und Marmoroberflächen denkmalgerecht restauriert.

Im September 2014 wurde die Schwimmhalle ihrem Charakter gemäß als öffentliches Sportbad wiedereröffnet.

Location
Finckensteinallee 73, 12205 Berlin-Lichterfelde
Client
BBB Infrastruktur GmbH & Co KG
Architects
Veauthier Meyer Architekten
Services
Objektplanung und Freianlagen LP 1–5, Denkmalpflegerische Bestandsaufnahme und Dokumentation
Completion
2014
Size
12.300 m2 BGF
Anerkennung
3. Preis im Heinze-Architekten-Award 2015 | Anerkennung im db Wettbewerb Respekt und Perspektive Bauen im Bestand Preis 2014